Vni. Special Considerations [Optional Services] TKLP
Please explain any special considerations not addressed in this Request for Proposal.
1. Facilitate and Run the Reliability Sessions: TKLP has considerable experience at manag
ing and running reliability sessions. We have included in this proposal only the time to
attend the session. There will be preliminary work, such as the preparation of the system
documentation for display on overheads to the attendees as well as preparation of the
event and fault- trees with notation as to what would normally be received in the bid speci
fications. It is these documents that will be used for the evaluation of the systems and its
components in these sessions. At the conclusion of the study, notes would be kept and the
reliability plan would be documented. This plan would create a basic guideline, scope, and
criteria for the four major elements that can affect reliability, the first being the operations
of the facility, the second being the construction, the third being the design, and the fourth
being the maintenance and exercising of the systems and the operating people. If TKLP is
to document the results of the two reliability sessions and at the conclusion of the second
session prepare the reliability plan, our fee would be $40,000.
2. Detailed Factory and Field Testing: TKLP has included traditional testing requirements
for their specifications. If FCTPA would like TKLP to develop detailed factory testing and
field testing, the field testing, including checkout system equipment tests, system tests, and
then system integration tests, the construction completion prerequisites would be defined
so that the test could be scheduled into the normal construction schedule. The instrumen
tation and false loading devices would be defined so that the cost for it could be included
as a requirement in the contractor's specifications. TKLP's fee for developing these de
tailed tests would be $40,000.
3. Agency Management: We have found that a very successful way to drive the completion
of a data center project is to use the final commissioning tests of construction to complete
the work rather than the traditional way, "space occupancy." This often forces a depth of
understanding of mechanical and electrical construction that exceeds that of the contract or
construction manager. TKLP has operated as an extension of their client or in an agency
agreement to work with the contractor or construction manager to reorganize their con
struction schedule toward the accomplishment of the final commissioning tests and the
activities that precede the tests in order to complete the systems. TKLP has then performed
the schedule reviews in the meetings, helped each one of the subcontractors organize their
work and crews to achieve the work necessary to accomplish the schedules, and then man
aged the setup of the auxiliary loads and instrumentation and managed the testing. To do
this, TKLP's fee would be $70,000.
4. Construction Cost Estimating; As part of this proposal, TKLP has proposed their estimat
ing within the framework of the AIA Owner/Architect Agreement B141, where the engi
neer would provide an opinion of cost. TKLP has individuals in their estimating department
who have considerable experience in the MEP construction field as estimators. We can
provide detailed estimates; and, in fact, our estimates have been used on an item-by-item
basis to negotiate labor and materials as a basis for negotiated contracts that were managed
Forest City Tech Place Associates for Full Engineering Services 05/06/92 [P237] vni-i