III. Similar and Current Projects TKLP
Name of Facility and Location Operations Center, Stanton, Delaware
Your role (MEP, consultant, etc.) Full Architectural and MEP Engineering Services
Client Contact J. P. Morgan Services Inc.
(Name, Address, Phone) Robert J. Hitchens, Jr., Vice President
500 Stanton Christiana Road
Newark, DE 19713-2107
302/992-1233
Architect Contact TKLP was the Architect of Record for this project.
(Name, Address, Phone)
Contractor or Construction Mr. Ted Dwyer
Manager Contact: EDIS
(Name, Address, Phone) 302/421-5700
Completion Date 1986
Gross Square Footage 330,000
Net Square Footage 240,000
Net Square Footage of 85,000
Data Center
Construction Budget $50,000,000
Actual Construction Cost $44,000,000
Owner Name and See client contact above.
Phone Number
Description
The primary elements of this 300,000 SF facility are the data center, which provides data
processing and communications network services; the operations center, which accom
modates large clerical operations using desktop computers; the Commons, which contains
shared facilities such as dining areas and administration; and the central plant, which
houses utility and support services. The Commons links the three-story data and opera
tions centers, which have raised access flooring throughout. The central plant is a separate
structure connected to the main building by a utility tuimel. Two utility feeds, a UPS
system, and emergency power generation provide backup for the critical electrical sys
tems. Preaction sprinklers and dry halon 1301 provide fire protection.
Forest City Tech Place Associates for Full Engineering Services 05/06/92 [P237] in-n