NYC 9/11 Public Portal Document
ADDENDUM No.
ADDENDUM TO CONTRACT NO. , dated , by and between The City of
New York (the “City”), acting by and throng the New York City Department of Environmental
Protection (“DEP”) and (“Contractor”).
Supply and Service Agreement
1. Article 6.5: ADD a new Paragraph C, as follows:
C. The Contractor shall be obligated to pay, satisfy and discharge any claims for theft,
disappearance or destruction of personal property made by the owners of buildings where work is
being performed by the Contractor, and/or by the owners/occupants of apartments where work is
being performed by the Contractor, to the extent such claims are not otherwise covered in fiill by the
proceeds of insurance maintained by the Contractor with respect to the performance of work
hereunder.
As security for the faithful performance by the Contractor of the foregoing obligation, DEP is
hereby authorized, in addition to the ten percent (10%) retainage referred to in Paragraph B above, to
deduct and retain a further five percent (5%) of the value of all work certified for payment in each
partial payment voucher, up to an aggregate total of $ 100,000. All monies deducted and retained by
DEP pursuant to this Paragraph C may be applied by DEP, in its sole and absolute discretion, to pay,
satisfy and discharge any such claims, if such claims are not otherwise paid, satisfied or discharged by
the Contractor within 30 days after demand by DEP. If at any time, because of payments made by
DEP out of such monies for such purpose, a total of less than $100, 352 is available to pay, satisfy or
discharge such claims, DEP is hereby authorized to resume deducting and retaining a fiirther five
percent (5%) of the value of all work certified for payment in each partial payment voucher, the intent
being that a fund of $100,000 shall always be available to DEP as security for the faithful performance
by the Contractor of such obligation.
DEP is authorized to continue using any monies deducted and retained pursuant to this
Paragraph C to pay, satisfy and discharge such claims for a period of six (6) months after completion of
all work hereunder. Upon the expiration of six (6) months after completion of all work under the
Contract, DEP shall refund any remaining portion of the monies deducted and retained pursuant to this
Paragraph C to the Contractor.
2. ADD a new Article 26, as follows:
Article 26, Waiver of Right to Assert Mechanic’s Liens.
NYC-WTC_000163476