The Project Monitor shall submit upon request to the EPA copies of the field notebook
as requested via fax or alternative format agreed upon and within two days of request.
Final air sampling shall be performed with 24 hours of final visual inspection. The
Project Monitor shall ensure that the Project Completion Form is completed for each
residence cleaned or sampled.
19. The Project Monitor will complete a daily report which documents site observations,
cleaning starts, continuations, completions, air sampling, recleaning and any delays or
difficulties encountered.
Deliverables
The Project Monitor shall enter appropriate data from the completed Project Completion
Form into the EPA Indoor Air web database or an agreed upon alternative electronic
format or website approved by EPA within 24 hours of activity.
20. EPA will notify residents of the results of sampling conducted as part of this project. No
other party is authorized to release residential or common area sampling results.
21. Any damage to or loss of private property that occurs during sampling or is caused by the
Monitoring Contractor or its employees while engaged in activities covered by this scope of
work is the responsibility of the Monitoring Contractor. The Monitoring Contractor is not
responsible for damage or loss caused by the acts of third parties not involved in activities
covered by this scope of work.
22. Copies of all reports. Cleaning Checklist, Inspection Checklists, Project Completion
Forms and chain-of-custody forms shall be submitted daily to the EPA.