electronic format or website approved by EPA within 24 hours of activity.
13. Pre-cleaning and Post-cleaning Wipe Sampling Procedures
a. The Project Monitor will collect pre-cleanup and post-cleanup wipe samples at 5
percent of the residences cleaned up to a maximum of SO residences as instructed by
EPA. This sampling will consist of the collection of 3 pre cleaning and 3 post
cleaning wipe samples for dioxin, total metals and mercury (Note: a separate wipe
sample is required for each parameter). Metals and mercury wipe samples will be
collected in accordance with procedures specified in HUD Appendix 13.1. Dioxin
wipe samples will be collected m accordance with the procedures specified in
ASTMD 6661-01.
b. The Mordtoring Contractor will document all the necessary information regarding
sampling activities, fill out all field logs, data sheets, and chain-of-custody forms.
The Monitoring Contractor shall use F2L for all sample and chain-of-custody
documentation. Samples must be labeled and accompanied withe •letedchain-of-
custody forms before shipping to Ihe designated laboratory. The label must include
the EPA Project Tracking Number. Samples will be packed, sealed and shipped daily
by courier for next day delivery to Paradigm Analytical Laboratories at: 2627
Northchase Parkway SE, Wilmington NC 28405
c. Persoimel collecting wipe samples shall be familiar with and experienced in the
collection of wipe samples using the specified sampling method.
Deliverables
Ihe Project Monitor will keep a field notebook and document sampling locations (including
a field sketch). The Project Monitor shall complete chain-of-custody forms and record the
number of wipe samples, EPA Project Tracking Numbers, the laboratory address, date, and
sample IDs in an agreed upon electronic format or website approved by EPA within 24 hours
of activity.
14. The Project Monitor shall schedule and oversee the cleaning operations of the Cleaning
Contractor. Prior to initiating the cleaning of any residence, common space or HVAC system
the Monitoring Contractor shall verify that the exterior of the building has been cleaned or
has been inspected and found to be free of debris from the collapse of the WTC or shall
obtain written authorization from EPA to proceed. No residential or common space shall
be cleaned until the HVAC system has been evaluated and cleaned as necessary. If a
scheduling problem arises, the Project Monitor should contact EPA. The Project Monitor
shall coordinate daily access for cleaning and sampling with residents, owners, the Cleaning
Contractor and sampling technicians.