Air Monitoring Requirements
iO0« For
125 Cedar Street
Project Monitoring
1. The project monitor shall provide oversight of clean-up activities to ensure compliance with project
specifications, tenants authorizations, and applicable rules and regulations. The project monitor
shall be present on site during all cleaning activities. The project monitor shall coordinate all
scheduling requirements for timely completion of the work (completion of work area preparation
and cleaning activities within three (3) weeks. The project monitor shall maintain the inventory of
valuable items in each unit as provided by tenants. A copy of the contractor requirements is
attached. For additional and specific tasks, refer to this attachment.
2. The project monitor shall provide daily monitoring of all work activities to insure compliance with
the scope-of-work, the applicable rules and regulations, and the contracts. This includes but is not
limited to the verification of worker certification status, the use of proper engineering controls and
appropriate work practices.
3. The project monitor shall direct corrective actions when appropriate and shall be responsible to stop
work until corrections are made. Findings must be reported immediately to DEP via telephone call.
Written notification of observation and corrective actions must be received by the DEP within 48
hours of telephone call.
4. A final report shall be submitted to the DEP within days of project completion. The report shall
clearly identify the work performed in each unit and shall include all laboratory reports, chain-of-
custody forms, field notes, copies of employee credentials (i.e. certificates), tenant and owner
authorizations, etc.