Comments on the New York City Department of Environmental Protection
Bureau of Environmental Compliance
Asbestos Contractor-Cleaning Procedures for 125 Cedar Street
1) Under Purpose it states-12 stories-approximately 52,000 square feet It is recommended that
this be changed to: 12 stories with a penthouse apartment, a basement and two commercial
spaces located on the first floor. The square footage of the building needs to be changed to better
reflect the actual number of square feet to be cleaned, not included in the above square footage
are ceilings, walls, staircase, elevator shaft (?), etc.
2) The Penthouse patio needs to be cleaned (was not cleaned during roofZfacade clean-up).
3) Approximately 100 linear feet of HVAC duct work in the commercial space needs to be
removed and disposed of as asbestos.
4) A contractor needs to be hired to recover the CPC’s from the refrigerators and air conditioners.
5) Deconning/enclosure of mail chute needs to be added.
6) Cleaning procedure for holes in floor, ceilings and walls.
TOTAL P.06