NYC 9/11 Public Portal Document
March 21, 2003
Athenica Environmental
COMMON AREAS
280 Rector Place- Started 3/20, Estimated Completion Date 3/24.
395 South End Ave.- Done except Laundry Room
375 South End Ave- 29 Floors Estimated Completion Date 3/24
355 South End Ave- Done 3/17 except Lobby (connected with 345 South End Ave), &
27* Fl- Re-cleaning Today
HVAC
280 Rector Place- Done 3/19
333 Rector Place- Done 3/6
345 South End Ave- Started 3/21 Estimated Completion Date 3/24
355 South End Ave- Done 3/17
375 South End Ave- Start Date 3/21 Estimated Completion Date 3/24
385 South End Ave- Done 3/20
395 South End Ave- Done Last Week