EP 1110-1-11
15 JUL 92
12. ADMINISTRATIVE CONSIDERATIONS. (independent of the abatement Contractor) who is
Because improper abatement may result in a hired by the Contracting Officer (CO).
hazard to building occupants, careful planning and
b. Contractor PreQua/ification. The most
diligent implementation of a project is essential.
effective means of ensuring high standards in
Por asbestos projects, the standard contractual
asbestos abatement is through prequalification of
relationship between the Contracting Officer's potential bidders. All potential bidders must have
Representative (CORI and the Contractor remains
successfully completed abatement projects simitar
the traditional construction overview practice. In
in size and complexity to the project being bid on.
addition, it is critical to foster cooperative onsite
A preliminary assessment of the quality and type
administration and coordination.
of abatement projects the potential bidders have
a. Contracting Officer's Representative (CORi. completed will be helpful in assessing their depth
of experience, quality of execution, and other
(II The asbestos abatement contract factors. All prequalifications should be reviewed
requires the COR to take a more active role than during the bidding stage by the CO and made a
the traditional construction or demolition contract part of the bid analysis.
allows. According to CEGS 02080, the COR is
c. Preabatement Notification to EPA/State.
responsible for monitoring contract compliance,
Preabatement notification is a submittal
accepting the Contractor's final clearance (before
requirement for the abatement. Per the revised
clearance air sampling) via a thorough visual
NESHAP, each owner or operator of an ACM
inspection, and normal inspection of workmanship
demolition and/or renovation site (covered by
and materials.
NESHAP) must, at least 10 working days before
(21 Failure to properly control the asbestos abatement begins, provide written notice of the
abatement procedure can result in contamination intention to demolish or renovate. The revised
NESHAP also requires a demolition/renovation
outside the work area. Because of the critical
value of onsite monitoring, the COR must be notification in a format similar to figure 1. Check
with the EPA region, the State, and the customer
directly involved in the oversight of preabatement,
abatement, and final clearance monitoring in order in order to determine who will submit the
notification, the Contractor or the Government.
to ensure that the Contractor's performance
meets quality standards. Should a hazardous d. Overnight.
situation arise (such as fiber counts exceeding
(II Contract enforcement. Enforcement of
established criteria or loss of containment area
the contract requirements by the COR
integrity), the COR will stop all work, investigate
encompasses both technical and administrative
the causes, and establish if a contamination event
functions, including the following:
has occurred, if contamination exists, work must
be terminated until a sampling program is (al Processing the Contractor's submittals
instituted to identify the source of contamination as listed in the Contractor's submittal register.
and the need for decontamination. The extent of
(bi Visual inspecting and monitoring of
contamination can be determined by establishing
the Contractor's work. Also, air sampling if
a thorough visual inspection and air-sampling
specified in the contract.
strategy (phase contrast microscopy (PCM) or
transmission electron microscopy (TEM)}. Work (cl Reviewing all Contractor's progress
will not recommence unless air samples prove reports and abatement daily log.
negative or until the affected areas have been ^di Preparing the final abatement report.
decontaminated and identified deficiencies
corrected. (21 Contract Submittals. The Contractor's
submittal register lists those items to be
(3) The COR's responsibilities described submitted to the CO (see CEGS 02080). There are
above may be performed by a Contractor four submittal categories: (1) those to be
•> 16 -