APPLICATION FOR PAYMENT
TO OWNER: City of New York
Department of Environmental Protection
59-17 Junctin Blvd., Flushing, NY 11373
FROM CONTRACTOR: Termon Construction, Inc.
388 Thrld Avenue
Brooklyn, NY 11215
PROJECT: WTC ARD APPLICATION NO. 024
Emergency WTC Date: August 22, 2003
Indoor Dust Remediation
Quadrant D, Manhattan, NY
1. ORGINAL CONTRACT SUM $ 4,199,499.40
2. Net change by Change Orders $ 279,298.00
3. CONTRACT SUM TO DATE $ 4,478,797.40
4. TOTAL COMPLETED &
STORED TO DATE $ 3,172,615.01
5. RETAINAGE
a. 10% of completed work $ 317,261.50
b. 5% per Addendum 3 $ 158,630.75
Total Retainage $ 475,892.25
6. TOTAL EARNED LESS
RETAINAGE $ 2,696,722.76
7. LESS PREVIOUS
CERTIFICATES FOR PAYMENT $ 2,668,714.08
8. CURRENT PAYMENT DUE $ 28,008.68
9. BALANCE TO FINISH,
INCLUDING RETAINAGE $ 1,782,074.64