May 02 03 03:11p p.2
Termon Construction Inc.
388 Third Avenue, Brooklyn NY 11215
Tel: (718) 694-0900
Fax:(718) 694-0200
Email: [email protected]
Mr. Rajappan Radhakrishnan, Director May 2, 2003
NYC Dept of Environmental Protection Send via fax: 718 595-3648
Asbestos & Lead Control Program
59-17 Junction Boulevard
Corona. New York 11368
Re: WTC ARD - Frequency and Distribution of apartments
Dear Krish.
As requested, Termon Construction Inc. (TCI) respectfully furnishes information necessary to develop compensation for TCI's
contract relative to working out of sequence and substantially different from our bid as formulated from the contract documents
and pre bid meeting discussions. IC! bid this contract and made every necessary arrangement to provide and supply the project
with manpower, supervision, equipment, materials and insurance needed to complete 20 apartments per day. Additionally, due
to the demographics of Quadrant D, TCI bid this contract and fully expected to clean multiple apartments within the same
buildings on the same day. IC! is requesting additional compensation for two situations
'1'Cl is requesting compensation of $500.00 per day for every working day of the contract, after work started, when less
than 10 apartments were scheduled in a given day and $1000.00 per day for each day when no apartments were scheduled.
This will pay for the overhead that was allotted for 20 apartments per day. Beginning October 21, 2002 (the first day
workers and equipment were mobilized at the project), through April 24, 2003 there has been approximately 32 weekdays
with no apartments scheduled. Additionally, there were approximately 85 days when less than 10 apartments were
scheduled and cleaned. Applying the above requested values to these numbers would yield additional compensation in the
amounts of, $32,000 and $42,500 respectively for a total of; $74,500.
2. TCI is requesting compensation of, $400.00 for the cost of a supervisor, for each occurrence where work was
performed in any less than 3 apartments within the same building. This does not take into consideration the loss
of efficiency and additional equipment required tomobilizo various locations. Beginning October 21, 2002 (the
first day workers and equipment were mobilized at the project), through April 24, 2003 there were
approximately 210 occurrences when only 1 or 2 apartments were cleaned within the same building. Applying
the requested compensation value of $400 to 2I0 occurrences would yield additional compensation of, $84,000.
Please take into consideration that there were a sufficient amount of apartments within each building to schedule multiple
apartments on the same day. Additionally, given the number of apartments in the program, there should not have been any day
with less than 20 apartments scheduled. Scheduling problems resulting from delays due to HVAC surveys or other reasons
were completely outside of our control.
We believe this letter provides you with the necessary information needed for you to establish the requested change orders. Of
course, should you have any questions, require additional information or want to schedule a meeting, just give us a call at 718
694-0900 or 917 873-7616.
'Sincerely yours,
TERMON CONSTRUCTION, INC
Thomas I-Icavey
Environmental & Construction Division
('C: Virginia Smyth, NYC DEP
Eric Wilson, US EPA
John Tancredi, SSC
Hazardous Waste Management.. Asbestos ♦ Lead Paint ♦• Mold
• Contaminated Soil ..Reconstruction •