Asbestos abatement technical specifications, 130 Cedar Street, July 2004

Machine-extracted title · confidence 100%

Technical specifications document prepared for asbestos abatement work at the 130 Cedar Street site.

NYC-WTC_000125579–000125652

Folder label: “130 CEDAR STREET

Page image
Scanned page image, NYC-WTC_000125635
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Asbestos Abatement Technical Specifications For 130 Cedar Street, New York, NY Note: Any penalties incurred for failure to comply with any of the above • regulations, will be the sole responsibility of the Contractor and his Sub- Contractors. The Owner(s) claims no responsibility for fines imposed due to the negligence of the Contractor.

3.2 Keep ACW separate from any other waste.

3.3 Keep ACW in a secured, enclosed and locked container.

3.4 If the Contractor has the intention of storing a quantity ACW greater than or equal to 50 cubic yards, the Contractor shall submit a written request and receive written approval from the Owner(s).

3.5 Prior to transport the Contractor shall:

a. Ensure that ACW has been sufficiently wet down.

b. Examine the integrity of the container's airtight seals.

C. Re-wet and re-package any damaged containers. Ensure that the person transporting asbestos waste holds a valid permit issued pursuant to New York State regulations.

3.6 Transport of ACW

a. Ensure that the ACW has been sufficiently wet down in a leak tight container.

b. Examine the integrity of the container's leak tight seal at a minimum of once per 24-hour period.

c. Re-wet and re-package any damaged containers.

d. Maintain at storage site an adequate supply of spare leak tight containers.

e. Maintain at storage site an adequate supply of amended water.

f. Keep ACW separate from any other waste.

g. Keep ACW in a secured, enclosed and locked container.

3.7 The Contractor or Sub-Contractor at the time of presenting for disposal of ACW shall comply with all applicable NYC DEP and NYS-DOL regulations issued pursuant to asbestos disposal.

3.8 For storage in the generation site:

a. Wet down all ACM waste in a manner sufficient to prevent all visible emissions of dust into the air. C] Prepared by JLC Environmental Consultants, Inc. Project No. 04-3271 Page 57

NYC-WTC 000125635

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000125635Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000127738 · Box DEP Box 52

Health and safety plan for Phase I deconstruction at 133-135 Greenwich Street and 21-23 Thames Street dated June 8, 2005.

Cited alongside this record in an Ask answer

Compare copies and versions →