Asbestos Abatement Technical Specifications
For 130 Cedar Street, New York, NY
Contractor shall be required to apply and receive approval for
r~ variances from the following NYCDEP Asbestos Control
Program regulations at a minimum to perform work in
compliance with applicable regulations: Sections 1-116(m), 1-
117(a), 1-118(a), 1-126(C).
9.0 General Cleaning Procedures
9.1 Visible accumulations of loose ACM shall be cleaned up as many times as
deemed necessary to prevent more than one bag of ACM to accumulate at
any time. This material shall be misted until such time as it can be properly
cleaned. At the end of each workday care shall be taken that no asbestos
containing debris is left overnight in the work area. Materials shall be
containerized using non-metallic dustpans or squeegees. HEPA vacuums
shall also be utilized to dean debris. Metal shovels shall not be used in the
work area to pick up or move accumulated waste material.
9.2 Visible accumulations of dust shall be cleaned of all surfaces in the work area
on a daily basis. Wet wiping and/or HEPA vacuuming shall be used for this
type of cleaning. The worker DES surfaces shall be cleaned according to this
method each day, as appropriate, after each shift change and meal break.
9.3 Excess water accumulation shall be avoided to prevent flooding of the work
area. If flooding occurs all work shall stop until the water is collected and
• disposed of properly.
10.0 Final Cleaning Procedures
10.1 Prior to commencement of final air clearance testing, these additional
cleaning precautions shall be undertaken to insure the area is ready for
clearance testing.
a) After removal of all visible accumulations of ACM, HEPA vacuuming
shall be performed on all surfaces. To pick up excess water and gross
saturated debris a wet-dry shop HEPA vacuum dedicated to asbestos
abatement may be used.
b) All surfaces shall be wet wiped at least once.
c) Upon completion of HEPA vacuum wet wiping, the cleaned layer of
surface barriers may be removed. Isolation barriers shall remain in
place throughout this operation.
d) The Contractor shall vacate the area and wait a minimum of twelve
(12) hours for airborne fibers to settle. At this point, all surfaces shall
be cleaned again using wet methods and HEPA vacuums. When this
is complete, the remaining plastic barriers shall be removed while the
isolation barriers remain in position.
Prepared by JLC Environmental Consultants, Inc. Project No. 04-3271 Page 55