• NYC DEPARTMENT OF ENVIRONMENTAL PROTECTION y r` ,.p I>ti N Asbestos Control Program 59-17 Junction Boulevard, 8m Floor, Corona, NY 11368-5107 ,4717itt4 /€,f I Building Ilept. or TRU No 2. ONLY 11r FOROFFICIALUSEONLY ASBESTOS PROJECT NOTIFICATION I • TYPEWRI FORM~I(tt " iKohc` (ASBESTOS INSPECTION REPORT) 1 ( e fee schedule)

When submitting this form at the NYC Department of Buildings, the original form and three (3) copies with original signatures are required. Submittal at the NYCDEP requires one copy of the form with original signatures. This form must be submitted to the NYC DEP not less than one week in advance of the start of abatement activities .

I. FACILITY

2. Address 156 William St Borough Manhattan Zip

AKA 51-55 Beekman St, 73-85 Ann St 3. Block 93 4. Lot 20

5. Type of Facility 6. Name of Building

II. BUILDING OWNER

7. Name 156 William St. LLC 8. Contact Person

9. Tel. # (212)_924-9690 Fax #

10. Address City State Zip

Ill. GENERAL CONTRACTOR

11. Name Tel. #

IV. ASBESTOS ABATEMENT CONTRACTOR

12. Name Benjamin Kurzban & Son Control 13. Contact Person Louie lannico

14. Federal Employer ID. L i 15. Tel. # (718) 531-2900 Fax # (718) 209-1808 • 16. Address 1248 Ralph Avenue City Brooklyn State NY Zip 11236

V. THIRD PARTY AIR MONITOR

17. Name Warren PanzaEtA E 1 1W EE iz.5 18. Contact Person M1 CLIAEL I0 LAM ti._._._._._.PII_._ _._._ 19. Federal Employer ID. 20. Tel. # (212) 922-0077 Fax it (212) 922-0630

21. Address 228 East 45th St City New yob State NY Zip 10017

22. Sample Analysis Laboratory 23. NYS DOH ELAP # _

VI. PROJECT INFORMATION J 24. Starting date for this portion of work 7/ 8 / D Projected completion date $ / OZ

Asbestos work schedule ❑ Monday ❑ Tuesday 0 Wednesday ❑ Thursday ❑ Friday 0 Saturday ❑ Sunday

Shift from: __ ❑ am 0 pm to ____ ❑ am ❑ pm

If other, specify

Access to inspect the premises must be provided during the work schedule indicated in this item. n +l ! 0 3 2002 r 25. Total amount of asbestos-containing material to be abated during this work 7D ,BANHM _:STGS/LEE- ?rGRAM 154 S7 ''Square Feet, and/or 0 Linear Feet T2 G ACP 7 2/2001 •

NYC-WTC 000110726

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000110726Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →