NYC 9/11 Public Portal Document
New York City Department of Environmental Protection
Bureau of Environmental Compliance
WTC Unoccupied Building Cleaning Program
125 Cedar Street
Scope of Work
Project #WTC UNC
A MANDATORY PRE-B1D meeting is scheduled for
August 28, 2002 at 1:00 P.M. at 125 Cedar
Street, Building Lobby, New York, N.Y. This conference will
include a walk through of the
entire building.
Background
A follow-up visit to 125 Cedar Street, a.k.a. 110 Liberty
Street, revealed debris and significant
dust accumulation present on surfaces throughout the
interior of the building. The interior
cleaning is to be accomplished by a licensed asbestos
abatement contractor.
Purpose
A New York State Department of Labor (NYSDOL)
licensed asbestos contractor with NYC DEP
and NYSDOL certified workers shall perform the clean
up of building interiors (12 stories, a
penthouse, and a basement-5,000 to 6,000 square feet per floor)
The entire building including
common spaces, storage spaces, residential and
commercial spaces (includes retail space on
Liberty Street) shall be included in the clean up
activities.
Contract Term
This contract shall be in force for 90 consecutive
calendar days from the DEP commencement
date. Contractors must be prepared to mobilize within
72 hours of the contract award.
Scope of Work
(I) All Work perfumed snail De in compliance with all
applh,;able, relevant, and appropriate
regulations, including but not limited to those of the
United States Environmental
Protection Agency (USEPA), the United States
Department of Labor, the New York State
Department of Labor (NYSDOL), the New York State
Department of Environmental
Conservation, the New York City Department of
Sanitation, the New York City
Department of Health (NYC DOH), and the New York City
Department of Environmental
Protection (NYC DEP).
(2) An ACP-7 form, asbestos project
notification form shall be submitted as required by
15, Chapter 1 of the Rules of the City of New Title
York (RCNY), directly to the NYC DEP
Asbestos Control Program prior to the start of work.
USEPA and NYSDOL notification
shall be submitted.
(3) A third party air monitoring firm shall
perform air sampling and provide project
oversight
(4) The asbestos contractor shall provide
suflicient equipment and experienced personnel to
complete work area preparation and cleaning activities of
the building interiors within three
I of 6