NYC 9/11 Public Portal Document
Anthony Ponzo
Vice President
Environmental Management
Site Management
Corporate Services
Merrill Lynch 2 World Financial Center
New York, New York 10281
212-236-7053
FAX 212-236-0041
[email protected]
June 19, 2002
Ms. Penny Theodorellys
Deputy Director, Asbestos Control Program
The City of New York Department of Environmental Protection
59-17 Junction Boulevard
Corona, NY 11368
RE: Request for Re-Inspection of Merrill Lynch Building Located at 222 Broadway (147-165
Fulton Street, 2-22 Ann Street)
Dear Ms. Theodorellys:
Merrill Lynch would like to formally request a reinspection of the exterior surfaces (roofs and
setbacks) of the Merrill Lynch building located at 222 Broadway (147-165 Fulton Street, 2-
22Ann Street) prior to power washing the exterior of the building. In a document dated May 3,
2002, the NYCDEP had indicated that visible debris was identified on the exterior of the above
referenced building. In response to this important issue, Merrill Lynch has implemented a
comprehensive cleaning program that has ensured that all debris has been removed in a manner
consistent with all public and occupational health regulations.
To assess the composition of the debris, Merrill Lynch retained the services of a New York State
licensed asbestos firm to collect bulk samples on the buildings roofs, setbacks, and window sills.
The results of all of the asbestos bulk sampling indicated that the majority of the debris was not
asbestos containing materials (ACM) and have been attached to this letter. Although the
majority of the samples did not indicate >1 % ACM, Merrill Lynch still utilized a certified
asbestos handler to perform the clean up of the debris from all areas. On the two setbacks (2) that
indicated debris at concentrations >1% ACM (floors 16A and 23), all necessary asbestos
abatement procedures were implemented. The results of the post abatement testing air testing
conducted on these setbacks are also attached at the end of this letter. All air samples indicated
airborne concentrations of <0.01 fibers per cubic centimeter (f/cc)
The clean up of the debris was conducted over the course of three (3) workdays, Saturday, May
18; Sunday, May 19 and Saturday June 15, 2002. Upon completing the debris clean up on June
15, 2002, Merrill Lynch is formally requesting a reinspection of the buildings exterior so that
power-washing procedures can commence.
NYC-WTC 000105910