Folder label / City-provided: Mayor's Office of Emergency Management 7 World Trade Center - 1, 7 & 23rd Floors Change Order #071 Amb. Job # S57-5175
2 documents · 4 pages
Change Order #71 for electrical work, 7 WTC, Feb 1999 ↗
2 pagesNYC-WTC_000168478 – NYC-WTC_000168479
Memo submitting Change Order #71 for $4,579 to install three-phase fields for circulation pumps at 7 World Trade Center.
Change Order #71 submission for pump wiring, Feb 1999 ↗
2 pagesNYC-WTC_000171639 – NYC-WTC_000171640
Ambassador Construction submits Change Order #71 to install two 3-phase fields for circulation pumps at the Mayor's Office of Emergency Management.