NYC 9/11 Public Portal Document
Part II - Environmental Community Monitoring Plan
133-135 Greenwich & 21-23 Thames Streets
Airtek Project 05-0701 - Rev 2 September 16, 2005
6.0 CORRECTIVE ACTION
If the validity of the data should become suspect during performance of the QA/QC procedures
identified in this plan, then corrective actions will be initiated. The actual trigger, as well as the
form of the appropriate corrective action, is dependent on the specific method/procedures, time at
which the error was detected and the type of the error that has occurred. For analytical
instruments, the corrective action may include:
• Recalibration or standardization of the instrument;
• Preparation of new standards; Repair or replacement of equipment, including columns,
detectors, etc.; and
• Reanalysis of samples.
The laboratory’s internal Standard Operating Procedures define corrective action. These
procedures will be requested by all laboratories providing analytical services to Airtek under this
project and will be appended t the QAPP when received.
Upon determining that deviations from the prescribed protocols contained in the QAPP have
occurred, the Laboratory Data Validation Officer will be notified. Within 48 hours, written
confirmation of the occurrence and the corrective action taken will be provided to the client.
7.0 ASSESSMENT AND OVERSIGHT
The following subsections describe assessment and oversight measures to be taken during data
collection. These actions are separate from the final data validation described in Section 5.1.
7.1 Assessments and Response Actions
The Data Manager will be responsible for routine assessment of data collection and for initiating
necessary response actions. The routine assessment will include review of data to ensure that
instruments are functioning and collecting information. Routine assessment actions will also
include review of the QC measures described in Section 3.6. Response actions will be initiated
immediately upon discovery of a problem. The Data Manager will perform these response actions
as needed to collect data that meet the project requirements.
The Project QA Officer will conduct occasional field oversight of sampling and analysis
activities. During al least one of these visits the Project QA Officer will submit performance audit
samples to be analyzed. During field oversight, the Project QA Officer will visually observe
sample collection and analysis to verify that the procedures outlined in this QAPP are being
followed and that any corrective action initiated previously is being continued.
Field documentation of samples, calibration, QC measures, and corrective action will also be
reviewed. In addition, the Project QA Officer will conduct at least one review of data and record
management systems at Purdue during the field monitoring period. During this review, the
Project QA Officer will verify that the data management procedures are being followed. Any
issues identified during these reviews will be discussed with appropriate personnel and addressed
immediately.
32
CITY_DEP_WORBY_CANNATA_SUBP_000087315
NYC-WTC_000425891
OCR can misread numbers and units. Confirm readings against the page image before using them.