NYC 9/11 Public Portal Document
GRACE CONTRACTING CORP.
151-45 6th Road, Whitestone, N.Y. 11357-(718) 767-9000 DATE: 2/27/02 DAY FINAL
DAILY WORK FORCE REPORT
Job Name & Location: World Trade Center
Contract No.
Weather Conditions
Labor Equipment
CLASSIFICATION QUANT. Description MANNED STANDBY IDLE
SUPERINTENDENT 1 CAT 966 LOADER
FOREMEN 1 CAT 365 GRAPPLER
PROJECT ENGINEER 2 CAT 375 GRAPPLER 1
SAFETY ENGINEER 1 CAT 375 BUCKET 1
LABORERS 3 HITACHI 750 GRAPPLER 1
IRON WORKERS HITACH11200 GRAPPLER 1
LOCAL 14 2 185 CFM COMPRESSOR RUNNING UNMANNED
LOCAL 15 3 235 HAMMER HOE RAM 1
CARPENTER MECHANICS TRUCK 2
CARPENTER FOREMAN TOOL TRUCK
TEAMSTERS (FUEL) 1 TOOLVAN
MECHANICS 2 ROLL OFF
HOUSE WRECKERS DUMP TRAILERS
LOW BED TRAILER
HIGH DECK TRAILERS
WELDING TRUCK 1
DELIVERIES: FUEL TRUCK 1
PICKUP TRUCKS 5
‘NOTE: LIGHT TOWERS RAN 2 HOURS LIGHT TOWERS 5
SITE MULE 3
TRUCKING DELAYED 1445-1630 WHILE TULLY/EROC DUMP TRUCKS
UNLOADED PRECAST ON WEST ST. 10 WHEEL DUMP TRUCK
FLASHING ARROW BOARD 1
OFFICE TRAILER/GENER. 1
CARGO BOXES 4
FLAT TRUCK 1
PUMP 2
■
Description of Work:
WORK COMPLETED_________________________________________________
CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF WTC COMPLEX
MAINTAIN TRAFFIC FLOW INTO AND OUT OF AREA___________ _________
CONTINUE LOGGING TRUCKS AND NUMBER OF LOADS OUT OF SITE