GRACE CONTRACTING CORP. 5 6th Road. Whitestone. N.Y. 11357- (718) 767-9000 DATE; DECEMBER 5, 2001 (DAY) FINAL DAILY WORK FORCE REPORT
Job Name & Location; World Trade Center Contract No. Weather Conditions ■ ■
■ Labor I I Equipment CLASSIFICATION QUANT. ItI Description MANNED STANDBY IDLE SUPERINTENDENT 1 ICAT 966 LOADER 1 PROJECT ENGINEER 2 I CAT 446 BACKHOE 1 OFFICE ENGINEER PAT 973 LOADER 1 FOREMEN 1 CAT 365 GRAPPLER 1 SAFETY OFFICER 1 CAT 375 GRAPPLER 1 LABORERS 24 HITACHI 750 GRAPPLER 1 IRON WORKERS 1 HITACHI 550 GRAPPLER 1 LOCAL 14 4 HITACHI 550 GRAPPLER 1 LOCAL 15 3 HITACH11200 GRAPPLER 1 CARPENTER 1 185 CFM COMPRESSOR 1 CARPENTER FOREMAN 1 235 HAMMER HOE RAM 1 TEAMSTERS 11 MECHANICS TRUCK 2 MECHANICS 2 TOOLTRUCK 1 HOUSE WRECKERS 7 TOOLVAN 1 ROLLOFF iDUMPTFtAILERS 7 LOW BED TRAILER IVERIES: AWISCO ■ HIGH DECK TRAILERS 3 ABCO ■ WELDING TRUCK 1 FUEL TRUCK 1 ■ PICKUP TRUCKS 8 ■ LIGHT TOWERS 13 SITE MULE 3 ■ DUMP TRUCKS ■ 10 WHEEL DUMP TRUCK ' FLASHING ARROW BOARD 1 ■ OFFICE TRAILER/GENER. 1 CARGO BOXES ■3
LIGHT TOWERS USED FOR 2.5 HOURS ' FLAT TRUCK 1 ■ PUMP 2 ■ ROLLER 1 ' FtAINMAKER/GENIE LIFT 1
Description of Work;____________________ _ _______________________________ _______________________________________ DELAYS: 2:30-4:00 PM ALL WORK STOPPED ~ LOAD OUT STEEL AND DEBRIS ■ MANNED TARPING AND TRIMMING STATIONS___________________________________ MANNED WATER STATIONS FOR DUST CONTROL MAI NTAIN TRAFFIC FLOW IN AND OUT OF AREA CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF NW CORNER OF TOWER 2 TO MEET AMEC’S ROADWAY CONTINUE BURNING OF THE SW CORNER COLUMN BEAMS ELEVATIONS: ALL MACHINES LEVEL B-5 253 ~ LOADS OUT 53 YUKE LOADS 35 ' GRACE CONTRACTING CORP Approved By; Tide: BY: superintendent
DAILY WORK FORCE REPORT 1205D.xls
CONFIDENTIAL CITY_2IMCl0 0_0 02149176 SUBJECT TO PROTECTIVE ORDER NO, 2, SEPT. 2008 NYC-WTC_000408036
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000291307
Daytime daily workforce summary for World Trade Center project; includes equipment list.
2 shared non-person entities · 1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305362
Day final daily workforce and equipment listing for World Trade Center site.
2 shared non-person entities · 1 shared topics · similarity 0.989
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000280771
Daily workforce and equipment list for World Trade Center, Dec 12, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.989
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000280092
Night daily workforce and equipment summary for World Trade Center, Dec 7, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.989
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000291404
Day final daily workforce report for World Trade site, Dec 15, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.988
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000280076
Daily workforce and equipment listings for World Trade Center, Nov 29, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.988
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305592
Daily workforce and equipment listing for World Trade Center site, December 2001.
2 shared non-person entities · 1 shared topics · similarity 0.988
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000280012
Daily workforce and weather note with equipment list for World Trade Center job, December 2001.
2 shared non-person entities · 1 shared topics · similarity 0.988
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305376
Day final daily workforce report for World Trade Center site, Dec 6, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.988
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305374
Day shift final daily workforce report for World Trade Center site, Dec 5, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.988
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000322142
Final daily workforce and equipment figures for World Trade Center project, December 6, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.988
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000388375
Daily labor/equipment roster for World Trade Center site, Dec 2001.
2 shared non-person entities · 1 shared topics · similarity 0.988
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Page similarity is temporarily unavailable or this page has no indexed vector.
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000291307
Daytime daily workforce summary for World Trade Center project; includes equipment list.
Similar indexed content
NYC-WTC_000305362
Day final daily workforce and equipment listing for World Trade Center site.
Similar indexed content
NYC-WTC_000280771
Daily workforce and equipment list for World Trade Center, Dec 12, 2001.
Similar indexed content
NYC-WTC_000280092
Night daily workforce and equipment summary for World Trade Center, Dec 7, 2001.
Similar indexed content
NYC-WTC_000291404
Day final daily workforce report for World Trade site, Dec 15, 2001.
Similar indexed content