Scope of Work.
• Remove and replace sand in playground area. Removal by use of vacuum truck. (See note A
below)
• Remove and replace sand in volleyball court area. Removal by use of vacuum truck. (See note A
below)
• Remove top 6” of soil in bocce court area. Removal by use of bobcat. (See note A below)
• Remove putting greens in miniature golf area. Power wash entire area.
• Replace damaged railing along Pier 25. Remove and replace all wood top handrails 500 If.
Power wash entire railing along pier. Repair damaged curb as needed.
• Excavate and remove temporary asphalt roadway. Excavate and remove all gravel under
temporary roadway. Excavate and remove of soil beneath gravel to elevation equal to bottom of
the adjacent paving stone. (Between N. Moore St. and School) (See note A below)
• Remove, cut and plug existing temporary drainage within the temporary roadway.
• Remove debris, patch as needed and power wash temporary bide path. Paint lines as required to
match the existing bike pa (between N. Moore St. and School) (See note A below)
• Bid to include any temporary barricades, railing or fencing that may be necessary to complete the
required work. Shall include any flagmen that may be required.
« Power wash new stone wall along bike path. Paving stone to remain in place.
• Note A: All debris and sand being removed shall be coordinated with Weeks Marine for loading
up and removal via barge. This removal work to take place during the week following the last
truckload from the WTC Recovery Site. Tentatively the last load is scheduled for 5/11/02,
therefore removal to take place between 5/12/02 and 5/17/02 (date of crane being demobilized
from Pier 25).
• All repair and replacement work to occur following the demobilization of the crane (5/17/02) from
Pier 25. All repair/replacement work to be complete by June 7, 2002.
• Working hours at pier 25 are between 7am and 7pm.
• Contractor to enroll in NYCDDC OCIP program with Liberty Mutual insurance.
• No sales tax to be included in the proposal.
TOTAL COST TO PERFORM THE WORK ENUMERATED ABOVE $572,000.00