Description of Work:____________________________________________________________________________
COMPLETED WORK
CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF TOWER 2 AND SOUTH OF MAIN CHILLER PLANT
MAINTAIN TRAFFIC FLOW INTO AND OUT OF AREA
MAN WATERING STATIONS FOR DUST CONTROL
EXPOSING THE PATH TRAINS__________________________________________________________________
2 MACHINES LEVEL B-6, EL 242, 3 MACHINES AT LEVEL B-5, EL253
LOADS OUT: 86
EUKES OUT: 226