Summary of City DOF procurement - DEP Title 11

Machine-extracted title · confidence 32%

Table of contents for Title 11 department and DEP-related sections.

NYC-WTC_000340361–000340367
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

(d) After the first cleaning, the work area shall be vacated for 12 hours to allow fibers to settle, rhen. all objects and surfaces in the work area shall be HEPA vacuumed and wet cleaned a second time. The remaining plastic surface barriers shall be removed, while the isolation barriers shall remain in position.

(e) After the second cleaning, the work area shall be vacated for 4 hours before wet cleaning and/or HEPA vacuuming all surfaces in the work area for a third cleaning.

(f) As a prerequisite to commencement of clearance air monitoring, a thorough visual inspection shall verify the absence of asbestos-containing waste material (e.g. dust).

(g) All containerized waste shall be removed from the work area through the decontamination enclosures and the holding area.

(h) All tools and .equipment shall be removed from the work area and decontaminated in the waste decontamination enclosure system. Cloths, mops, and other cleaning aids shall be disposed of as asbestos-containing waste material.

(i) After successful clearance air monitoring (see §1-31 et seq.), the isolation barriers shall be removed in conjunction with the use of a HEPA vacuum.

Subchapter G

Pre-Demolition Abatement Activity Procedures

1 Applicability 2 Work Procedures

Part 1

Applicability

§1-120 Applicabiliiv of Regulations to Pre-Demolition Abatement Activities

§1-120 Applicability of Regulations to Pre-Demolition Abatement Activities. The following regulations shall apply to pre demolition abatement activities;

§§l-0l through 1 61 General Regulations 1-82 Worker Decontamination Enclosure System 1-83 Waste Decontamination Enclosure System 1-91 through 1-94 Work Place Procedures 1-102 ACM Disturbance, Handling and Removal Procedures 1-105 Glovebag Procedure 1-106 Tent Procedure

CITY_21MC1OO_OO9279693

NYC-WTC_000340367

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000340367Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →