GRACE CONTRACTING CORP. I
151-45 6th Road, Whilestona, N.Y. 11357-(718) 787-8000 DATE: DECEMBERS, 2001 (NIGHT FINAL)
i
DAILY WORK FORCE REPORT I
I
i
Job Nams & Location: World Trads Csntsr
Contract No.
Weather Conditions
Description of Work:
LOADS OUT: 26 DUMP TRAILERS/HIGH BEDS; 33 EUCLIDS
LOAD OUT STEEL AND DEBRIS,
MAN TARPING AND TRIMMING STATIONS:
MAN WATER STATIONS FOR DUST CONTROL
CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF NW CORNER OF TOWER 2 TO MEET AMEC'S ROADWAY.
CONTINUE BURNING OF THE NORTH WALL COLUMNS
ELEVATIONS; ALL MACHINES LEVEL B-5 253
DELAYS; TOTAL DELAYS OF MACHINES IN HOLE APPROXIMATELY 1 HR FOR FDNY;
FREON RECOVERY FROM 7-10:30 PM, NO DUMP TRAILERS LOADED._________________________________________ '
GRACE CONTf^CTING fiORP
Approved By:
Jille: BY;
SUPERINTEND^T
For;
DAILY WORK FORCE REPORT 1206N.xls
CITY_21MC100_0 04780332
NYC-WTC_000291377
OCR can misread numbers and units. Confirm readings against the page image before using them.
NYC-WTC_000291377Source: NYC Law Department, mirrored locally