Night preliminary daily crew and equipment listing for World Trade Center site, Jan 24, 2002.
1 shared topics · similarity 0.993
machine-extracted · confidence unavailable · Check page ↗Night shift daily workforce and equipment at World Trade, Jan 21, 2002.
NYC-WTC_000280830OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
GRACE CONTRACTING CORP. 151.45 6in Road. Whitestone. N.Y. 11357.(718)767.9000 DATE: 1/21/02 NIGHT PRELIMINARY
DAILY WORK FORCE REPORT
Job Name & Location: World Trade Center Contract No. Weather Conditions
Labor 11I Equipment CLASSIFICATION QUANT, irI Description MANNED STANDBY IDLE SUPERINTENDENT CAT 966 LOADER 1 PROJECT ENGINEER 1 CAT 973 LOADER 1 OFFICE ENGINEER CAT 365 GRAPPLER 1 FOREMEN 2 CAT 375 GRAPPLER 1 SAFETY OFFICER___________________________ CAT 375 GRAPPLER 1 laborers 13 HITACHI 750 GRAPPLER 1 IRON WORKERS HITACHI 550 GRAPPLER 1 local 14 5 HITACHI 550 GRAPPLER 1 LOCAL 15 5 HITACHI 1200 GRAPPLER 1 CARPENTER 185 CFM COMPRESSOR 1 CARPENTER FOREMAN 235 HAMMER HOE RAM TEAMSTERS (FUEL)__________________ 1 MECHANICS TRUCK TEAMSTERS (FLATBEDS, DUMPS. AND EUKES) 10 TOOL TRUCK MECHANICS 1 TOOL VAN HOUSE WRECKERS ROLL OFF DUMP TRAILERS LOW BED TRAILER HIGH DECK TRAILERS DELIVERIES; WELDING TRUCK FUEL TRUCK 1 PICKUP TRUCKS 3 LIGHT TOWERS 5 SITE MULE 5 DUMP TRUCKS 3 10 WHEEL DUMP TRUCK FLASHING ARROW BOARD OFFICE TFtAILER/GENE^ 1 IcARGO BOXES ' T FLAT TRUCK 3 PUMP ~ RAINMAKER/GENIE LIFT 2 1
Description of Work:_________________________________________________ PRELIMINARY/ANTICIPATED WORK__________________________________ CONRNUE_REMOYING_DE8RIS_FROhlLOWERJ^BVeL^ MAINTAIN TRAFFIC FLOW INTO AND OUT OF AREA
GRACE CONTRACTING CORP Approved By; Title: For; SUPERlNTEI^eNT
DAILY WORK FORCE REPORT0121N.xls
CITY_21MC1OO_OO39187O4
NYC-WTC_000280830
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000305465
Night preliminary daily crew and equipment listing for World Trade Center site, Jan 24, 2002.
1 shared topics · similarity 0.993
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000267323
Night preliminary daily workforce with labor and equipment details for World Trade Center.
1 shared topics · similarity 0.993
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429412
Night shift daily workforce and equipment details for World Trade site on 1/27/02.
1 shared topics · similarity 0.993
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305072
Daily workforce and equipment entries for World Trade Center site, Jan 2002.
1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000342304
Night shift workforce and equipment at World Trade, Jan 20, 2002.
1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305180
Daily staffing and equipment tally for World Trade, Jan 27, 2002.
1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305458
Night preliminary daily crew and equipment listing for World Trade Center site, Jan 28, 2002.
1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000279857
World Trade Center night preliminary daily workforce and equipment listing, Jan 26, 2002.
1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000267309
Night shift labor/equipment roster for World Trade Center site.
1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000356568
Daily labor/equipment roster for World Trade site, Jan 26, 2002.
1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000356558
Daily labor/equipment roster for World Trade site, Jan 21, 2002.
1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000388158
Night preliminary daily workforce and equipment at World Trade Center site.
1 shared topics · similarity 0.990
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
NYC-WTC_000305465
Night preliminary daily crew and equipment listing for World Trade Center site, Jan 24, 2002.
Similarity score 0.997 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000267323
Night preliminary daily workforce with labor and equipment details for World Trade Center.
Similarity score 0.997 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429412
Night shift daily workforce and equipment details for World Trade site on 1/27/02.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305072
Daily workforce and equipment entries for World Trade Center site, Jan 2002.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000342304
Night shift workforce and equipment at World Trade, Jan 20, 2002.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305180
Daily staffing and equipment tally for World Trade, Jan 27, 2002.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000305465
Night preliminary daily crew and equipment listing for World Trade Center site, Jan 24, 2002.
Similar indexed content
NYC-WTC_000267323
Night preliminary daily workforce with labor and equipment details for World Trade Center.
Similar indexed content
NYC-WTC_000429412
Night shift daily workforce and equipment details for World Trade site on 1/27/02.
Similar indexed content
NYC-WTC_000305072
Daily workforce and equipment entries for World Trade Center site, Jan 2002.