Description of Work:___________________________________________________________________________________
J__
DELAYS: 2:30-4:00 PM ALL WORK STOPPED
LOAD OUT STEEL AND DEBRIS
MANNED TARPING AND TRIMMING STATIONS____________________________________________________________
MANNED WATER STATIONS FOR DUST CONTROL________________________________________________________
MAINTAIN TRAFFIC FLOW IN AND OUT OF AREA_________________________________________________________
CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF NW CORNEROFTOWERJJTOMEET AMEC'S ROADWAY
CONTINUE BURNING OF THE SW CORNER COLUMN BEAMS
ELEVATIONS: ALL MACHINES LEVEL B-5 253
LOADS OUT 53 YUKE LOADS 35
GRACE CONTRACTING CORP^
Approved By:
Title:
For SUPERINTENDENT
DAILY WORK FORCE REPORT 1205D.xls