GRACE CONTRACTING CORP.
151.45 6fh Road, WhHaslone, N.Y, 11357-(718) 767-9000 DATE: 2/5/02 DAY FINAL
DAILY WORK FORCE REPORT
Job Name & Location: World Trade Center
Contract No.
Weather Conditions
Labor Equipment
CLASSIFICATION QUANT. _______ Description______ MANNED STANDBY IDLE
SUPERINTENDENT 2 CAT 966 LOADER 1
PROJECT ENGINEER 2 CAT 365 GRAPPLER 1
FOREMEN 1 CAT 375 GRAPPLER 2
SAFETY OFFICER 1 HITACHI 750 GRAPPLER 1
LABORERS 13 HITACH11200 GRAPPLER 1
IRON WORKERS 185 CFM COMPRESSOR *SEE NOTE
LOCAL 14 4 235 HAMMER HOE RAM 1
LOCAL 15 5 MECHANICS TRUCK 2
CARPENTER TOOL TRUCK 1
CARPENTER FOREMAN 1 TOOL VAN 1
TEAMSTERS (FUEL) 1 ROLL OFF
TEAMSTERS (FLATBEDS, DUMPS, AND EUKES) 14 DUMP TRAILERS 8
MECHANICS 2 LOW BED TRAILER
HOUSE WRECKERS 1 HIGH DECK TRAILERS 2
WELDING TRUCK 1
FUEL TRUCK 1
PICKUP TRUCKS 8
DELIVERIES; LIGHT TOWERS 5
SITE MULE 3
NOTE: LIGHT TOWERS USED 2.5 HOURS DUMP TRUCKS
135 CFM COMPRESSOR RAN UNMANNED 10 WHEEL DUMP TRUCK
FLASHING ARROW BOARD
OFFICE TRAILER/GENER. 1
CARGO BOXES 4
FLAT TRUCK 1
PUMP 2
Description of Work:________________________________________________
ANTICIPATED WORK
CONTINUED REMOVING DEBRIS FROM LOWER LEVELS OF WTC COMPLEX
MAINTAINED TRAFFIC FLOW INTO AND OUT OF AREA
CONTINUED LOGGING TRUCKS AND NUMBER OF LOADS OUT OF SITE
LOADS OUT:_____________________________________________________
EUKES OUT:
GRACE CONTRACTING CORpI
Approved By; BY:
Title:
For: SUPERINTENDENT
DAILY WORK FORCE REPORT0205D.xls