Consultant meeting minutes: 7 World Trade Center project status, October

Machine-extracted title · confidence 95%

Minutes from consultant meeting #14 discussing project status, steel delivery, and fuel oil piping at 7 World Trade Center.

NYC-WTC_000173688–000173689

Folder label: “MINUTES OF CONSULTANT'S MEETING #14

Page image
Scanned page image, NYC-WTC_000173688
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

•SMBASSADOR CONSTRUCTION CO, INC.

MINUTES OF CONSULTANT’S MEETING #14

PROJECT: Mayor’s Office of Emergency Management 7 World Trade Center -1. 7 & 23rd Floors Amb. Job#S57-5175

DATE; October 20. 1998

PRESENT; Martin Schneider Ambassador Jay Koven Ambassador Jack Klein Ambassador Bill Daly Ambassador Walter Weems SPI Glenn Pymento DCAS Josep Domingvez DCAS Bob Melaniff DITT Juan Mejia Swanke Hayden Connell John Hughes OEM Philip Moy Motorola

1. I^OJECrSTATUS Tst Floor: - Chopping for fuel oil piping on hold due to resolution of steel hits1^^^^5 v ______ - Steel to be delivered Monday, 10/26/98. — 3 ’ --------- - Tfh Floor: - Ambassador to set up electric survey. —’ - Drywall partition work to start this week. s uk- OXT So - Water storage tank material has been delivered. - Steel for emergency generator and water tank dunnage to be delivered this-^irTS- _____________ week. J'- — ~~--------- Ambassador to schedule duct removal and reinstallation. jD 23rd Floor.- Plumbing roughing 95% - Ceiling and soffit work 85% —— ------ 1 - Hurricane wall steel 80% - Hurricane wall framing 60% - Cooling towers are in NY area - A/V cable work started - Telephone cable work started Roof: - Steel to be delivered next week - Metal panel walls have been released r

2. GENERAL - Ambassador advised that they will release the metal panel. Ambassador will advise contractor to match color of existing panels - Ambassador advised that emergency generator will be shipped 10/23/98 - Ambassador advised that SPI requested oil protection in the emergency generator /room Continued... 317 MADISON AVENUE. NEW YORK. NY 10017, 212 922 1020, FAX 212 949 9762

NYC-WTC_000173688

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000173688Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Consultant meeting minutes #15 for OEM, Oct 1998 · Box 7DCAS

NYC-WTC_000173580

Minutes from Ambassador Construction Co. regarding steel interference solutions and project status at the Mayor's Office of Emergency Management.

4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.968

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000173659 · Box 7DCAS

Record of a consultant meeting held on October 13, 1998, covering shop drawing reviews and project status updates.

Similar indexed content

Compare copies and versions →