Same-box records
Change order #001 for OEM Inergen reserve system, Dec 2000 · Box 7DCASNYC-WTC_000171486
Submission of change order #001 by Ambassador Construction to install a connected reserve Inergen supply system at the Mayor's Office of Emergency Management.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.977
Change Order #107 for OEM Painting Work, Dec 1999 · Box 7DCASNYC-WTC_000171592
Ambassador Construction submits Change Order #107 for painting the smoke room at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.957
Memo approving change order 113, June 2000 · Box 7DCASNYC-WTC_000171293
City memo approving $3k for installing self-closing hatch mechanism in tank room fire system.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.956
Proposal for switch installation in tank room, Nov 2000 · Box 7DCASNYC-WTC_000171482
Cost proposal submitted by Ambassador Construction Company to install a new lock-out switch for the Inergen system at 7 World Trade Center.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.956
Change Order #054 for OEM project at 7 WTC, Jan · Box 7DCASNYC-WTC_000171383
Change order #054 from Ambassador Construction dated January 18, 1999 for computer equipment relocation at 7 World Trade Center.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.956
Change order #108 cover letter, Dec 17 1999 · Box 7DCASNYC-WTC_000171573
Ambassador Construction cover letter dated December 17, 1999 submitting change order #108 for video cable connections at the Mayor's Office of Emergency Management.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.955
Cover Letter for Change Order #112, 7 WTC, Feb 2000 · Box 7DCASNYC-WTC_000171517
Cover letter submitting Change Order #112 for the replacement of an anti-siphon valve with a check valve at 7 World Trade Center.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.955
Proposal for tank room switch installation, November 2000 · Box 7DCASNYC-WTC_000171280
Contractor proposal from Ambassador Construction dated November 16, 2000 to install a lock-out switch for $1,221 at the Mayor's Office of Emergency Management.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.954
Change Order #48 for access door at 7 World Trade · Box 7DCASNYC-WTC_000168555
Memo submitting Change Order #48 to furnish and install a new access door in room 23-51.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.953
Change Order #46, 7 World Trade Center, Jan 1999 · Box 7DCASNYC-WTC_000172216
Submission of Change Order #46 for $2,168 to provide power supply in room 23-50 at 7 World Trade Center.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.952
Change Order #67 for computer work, 7 WTC, Feb 1999 · Box 7DCASNYC-WTC_000168489
Memo submitting Change Order #67 for $2,894 to furnish cords and relocate speaker strobes at 7 World Trade Center.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.951
Change Order #025, 7 World Trade Center, Nov 1998 · Box 7DCASNYC-WTC_000168612
Ambassador Construction submits Change Order #025 for structural support work on the roof of 7 World Trade Center.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.951