AMBASSADOR CONSTRUCTION CO, INC.
Mayor’s Office of Emergency Management
Consultant’s Meeting Minutes #9
September 15, 1998
Page Two. . .
-te U YttX FA
3. PROJECT STATUS
1st Floor
forwork
Fuel oil tank
-- Chopping to start
fuel oil piping is on hold pending inspection by C^n-Ed. /*/ /
- Steel has been released for fabrication. Field measuring to be completed
9/18/98.
7th Floor
- Silverstein Properties, Inc. advised that mechanical drawings from Cosentini
will be delivered this week .
- Ambassador is coordinating equipment layout.
- Layout and framing is 95% comple^ *
- Drywall installation is 75% complete.
- Taping is 35% complete.
- Sprinkler mains and branches are 85% complete.
- Black iron for ceilings is 80% complete.
- Plumbing roughing is 70% complete.
- Plumbing drains are 70% complete.
- Duct installation is 80% complete.
- Electrical riser work is 60% complete.
- Ceiling and soffit work is 25% complete
- Acme walls are released. Delivery in (3) weeks.
- Hurricane wall is released, to start this week. ------
Roof
- Ambassador to start the week of 9/21/98.
4 RFl STATUS^ <0^
- See list attached.
5. GENERAL
- Silverstein Properties, Inc. to receive mechanical drawing of the 7th floor this week.
- DCAS asked the status of electrical meter as per Silverstein Properties, Inc.’s
comments. Cosentini to follow up.
- Ambassador advised that there are a lot of field conditions regarding steel plates for
hurricane wall. Ambassador, Swanke Hayden Connell and Cantor are coordinating.
Continued.../