NYC 9/11 Public Portal Document
TO: Michael Gilsenan
NYCDEP
FROM: Nancy Jeffery (NYC DOHMH)
Robert Chinery (NYSDOH)
DATE: August 2,2002
SUBJECT: Comments on SOWs for: WTC Indoor Dust Cleaning Program Cleaning
and Monitoring Contracts
We have reviewed the draft July 30,2002 scope of work for the two contracts and have
the following comments. Comment 3 specifically addresses the proposed procedures for
addressing mold issues:
Monitoring Contract Scope of Work
1. Introduction (page 1) 2"^ Paragraph, last sentence, should be modified to
reflect the fact that in some of the residences/buildings, dust wipe samples
will also be collected. Currently, the sentence states that contractors will
follow-up with asbestos and asbestos air sampling only.
2. Deliverable 7 c. vi. (page 4) states that the project manager will advise EPA of
other circumstances that may require deviation from the specified cleaning
and monitoring procedures. The question we raise is related to what will be
the incentives for the project monitor or cleaning contractor to look for non
routine reservoirs of potential WTC-related dust and debris? For example, it’s
not clear whether the cleaning contractor would be paid a fiat fee per
residence/building or whether there would be incentives to search out other
possible dust reservoirs in the buildings.
3. Deliverable 8 (page 5), last sentence states that cleaning will not proceed in
areas where mold is observed until potential hazards are evaluated and
addressed if necessary. The sentence is very broad and is not clear who would
make sure the mold issues are addressed. As addressing long-standing mold
issues can take a very long time, we suggest that the project manager should
notify EPA and contact DOHMH if visible mold conditions exist so they can
be evaluated. The project managers should also be provided a copy of and be
familiar with the DOH’s Mold Assessment and Remediation Guidelines so
that common bathroom mold conditions do not stop the important clean-up
work from proceeding.
4. Deliverable 9 (page 5), the word “paint” is missing from the 3*^ sentence.
5. Deliverable 10 (page 5), sentence states that HVAC systems will be
evaluated to determine if these systems have been impacted by dust or debris
NYC-WTC_000163232