preventing inhalation exposure to asbestos and other fibrous materials, as well as other
potential indicator compounds.
Program: EPA will clean one unoccupied building to confirm and test the techniques.
Projected Cost: $5 million. This cost is higher than in the above efforts because it will involve
sampling for several potential indicators of WTC related contamination before work is
commenced, will involve use of several modifications of cleaning techniques with post
clean up sampling and re-cleaning if necessary.
4. Cleaning of Debris-Laden Unoccupied, Uncleaned Buildings
Objective: Since the debris removal from the immediate areas of destruction in the WTC complex
is nearing completion, the remaining unoccupied, uncleaned buildings must be cleaned.
This will prevent debris/dust from being re-entrained in air and/or re-contaminating the
nearby areas with debris/dust.
Program: NYC will clean the remaining unoccupied (residential and commercial), uncleaned
buildings near the WTC site that contain WTC-debris. NYC will work with building
owners to determine reasons that these buildings have not been cleaned yet. If building
owners are not able to expeditiously clean their property, NYC will proceed.
Projected Cost: $20 million, based upon estimates approximately $2 million/building for 10
buildings. Inventory of buildings is being identified by NYC and may be decreased as a
result of NYC=s efforts to get building owners to conduct clean up.
Status ofRequestfor FEMA mission assignment: Awaiting initial FEMA feedback
5. Clean Up of Exteriors of Buildings with Residual Debris/Dust
Objective: To eliminate remaining debris/dust resulting from the WTC collapse on building
exteriors in Lower Manhattan thereby assuring this material will not become re-entrained
in the air at a future time, thus creating a potential exposure to the public.
Program: NYC DEP will contract for the cleaning of file exteriors of approximately 250
buildings in Lower Manhattan. EPA, NYCDEP and OSHA will oversee contractors.
Projected Cost: NYC $10.28 Million
Project Period: April 2002 fiirough November 2002
B) Longer Term:
< Identify potential compounds of concern, which resulted from the WTC collapse and
subsequent fires and for which there is ambient data to suggest potential concern and
which have not been evaluated in the indoor environments thus far.
< Conduct sampling of the potential compounds of concern to establish a NYC specific
background data set.
< Create a Data system for Organizing Existing Information Collected by NYC from the
Private Sector on environmental testing results and clean up activity.
3
NYC-WTC_000162089