Gilsenan, Michael
From: [email protected]
Sent: Tuesday, October 08, 2002 2:42 PM
To: Gilsenan, Michael
Subject: Meeting with Counsel for Independence Plaza on October 3
Dore LaPosta suggested that I forward this message to you and that I
give Richard Leland, Esq, of Kramer Levin your phone number. He wants
to raise IPN's issues, noted in paragraphs 3 and 4 below, with a manager
at DEP to see if you can modify City's agreement with the contractors.
Kathy Callahan was not able to reach you by phone yesterday to discuss
the issues raised by IPN's counsel. I believe that FranK Schiano
discussed this with you.
Forwarded by Beverly Kolenberg/R2/USEPA/US on 10/08/02 02:31 PM
Beverly
Kolenberg To: Kathy Callahan/R2/USEPA/US@EPA,
Dore
LaPosta/R2/USEPA/US@EPA, Michael
Brescio/R2/USEPA/US@EPA,
10/03/02 05:59 Arlene Anderson/R2/USEPA/US@EPA
PM cc: Thomas Lieber/R2/USEPA/US@EPA,
Paul
Simon/R2/USEPA/US@EPA
Subject: Meeting with Counsel for
Independence Plaza on
October 3
Tom Lieber and I met with the following representatives of Independence
North: Ezra Goodman, counsel for real estate and contracts issues,
Richard Leland, counsel for environmental issues and his associate Toni
Ferrucci, and Debbie Dolan, Manager from Hudson River Management IPN's
management company to discuss the issues that they believe remain to be
resolved.
We were informed that a contract for sale for the IPN property has been
signed by Duane Street Associates, the owner with an unnamed buyer. For
that reason, among others, counsel want to insure that no liens or
violations are placed on the buildings as a result of the work that will
performed by the cleaning and monitoring contractors.
At the conclusion of the meeting counsel said that they would like to
bring their contract concerns to someone at a high level at NYCDEP to
advocate for the proposed contract language they want. In sum, Goodman
suggested that the language in the city contract provide that any lien
on the property filed by a subcontractor or materialman be satisfied
within 30 days by the contractor. As to liens on the property filed by
the contractor on the property, he would like the City to discharge the
lien within 30 days or failing to do so, pay the legal expenses of the
property owner if the matter is litigated.
For violations that are filed by the City or other agency on the
property due to the activities of the contractors, they were seeking to
get violations removed promptly and indemnification for their expenses.
They wanted to formally incorporate the information in the fact sheets
by reference into the consent to access forms, and we said the language
in the consent forms could be changed.
1
NYC-WTC_000160338
OCR can misread numbers and units. Confirm readings against the page image before using them.