of the baseboard heaters in common spaces, nor the cleaning of ‘through the wall HVAC
Units’ are separate or additional items and neither are reimbursable under the terms of the
Contract.
Pursuant to Section 4 of Article 19 “Resolution of Disputes,” your client was to submit its
dispute “within thirty (30) days of receiving written notice of the determination or action that
is the subject of the dispute.” Since Mr. Radhakrishnan advised your client that neither the
baseboard heaters in common spaces, nor the “through the wall HVAC Units” were extra
work on September 23, 2003, the time to submit such dispute has long since passed. Your
client’s appeal was submitted almost one year after the Bureau’s Determination. This is not
only unacceptable, but violates the terms of the Contract.
5. Additional Insurance Premium
Termon’s request to recoup additional insurance premiums is unheard of. Given the
significant amount of insurance required under this Contract, all Contractors were told to
include the premiums in their bids. As your client was well aware, the Contract enabled
business and homeowners to call the DEP/EPA hotline to request clean up and remediation
services. It was estimated that approximately ten thousand (10,000) people would request
such services. However, at no time did the “DEP materially reduce[ ] the amount of work that
was assigned” nor did DEP end the contract “prematurely on June 1, 2003.”
6. Removal and Disposal of Wall-to-Wall Carpeting
Your client received a letter from Virginia Smyth, Bureau Chief Contracting Officer, dated
July 9, 2003, wherein Ms. Smyth responded to your client’s letters of April 7,2003 and May
2, 2003. As stated above, pursuant to Section 4 of Article 19 “Resolution of Disputes,” your
client was to submit its dispute “within thirty (30) days of receiving written notice of the i
determination or action that is the subject of the dispute.” Ms. Smyth advised your client that
the disposal of items is within the scope of the Contract” and that there would be no
reimbursements for this Contract work. Again, the time to dispute such a finding has long
since passed. Your client’s appeal was submitted well over one year after the Bureau’s
Determination.
As set forth under Section 1 above, the Department shall process the payment of outstanding
invoices and the release of the retainage, so long as a proper assignment of payment and a
request for the release of retainage are submitted. Accordingly, as to that item, your Dispute
is granted, as modified by the amount approved for payment of the final invoices from
USEPA.
However, as to the remaining requests, your Dispute is hereby denied. Please be advised that
in accordance with Article 19 of the Standard Construction Contract, I have conducted the
requisite investigation. I hereby determine that NYCDEP’s prior determinations that
additional compensation for items that were part of the Contract work, communicated to
Termon well over a year ago, were appropriate.
<