Avaltroni, Robert
From: Gilsenan, Michael
Sent: Friday, March 07, 2003 9:08 AM
To: '[email protected]'
Cc: Avaltroni, Robert; Radhakrishnan, Krish
Subject: Numbers requested
Walter,
As you requested, please find the number of apartments that have been cleaned as of Monday, 3/3.
Clean & Test Test Only
Quad A 555 56
B 912 87
C 375 33
D 227 218
2,069 394
As a result of our meeting the last two weeks, the following has occurred:
59 letters were sent to building owners who signed up for whole building clean-up and who had not returned their access
agreements (common spaces, HVAC)
19 of the 59 buildings dropped out of the program; 2 buildings still pending decision, due 3/7/03
Quad A
390 express mail letters were sent to residents starting the two-week clock (mailed by 2/28/03). Received commitment
from project monitor to mail balance by 3/7
Quad B
348 express mail letters were sent to residents starting the two-week clock (mailed by 2/28/03)
* Note, This Quad is almost finished. Has cleaned 912 apartment, to date
Quad C
410 express mail letters sent and 520 telephone contacts made starting the two-week clock on
930 residents (mailed and called by 2/28/03)
Quad D
83 express mail letters were sent. This Quad is behind due to HVAC/exhaust issues but, as discussed yesterday, they
are ready to start cleaning common spaces/HVACs in buildings that represent 80% of residents' requests. We also
required a cleaning schedule from them, so that the group can be apprised of when apartments become available for
scheduling by the air monitor.