Program: EPA will clc5’i one unoccupied building to confirm and test the techniques.
Projected Cost: $5 million This cost is higher than in the above efforts because it will involve
sampling for se\ c 1 potential indicators of WTC related contamination before work is
commenced, will in\ oh. c use of several modifications of cleaning techniques with post
clean up sampling and re-cleaning if necessary.
Status ofRequestfor FF^fi mission assignment: Submitted as revised 4/11/02. Awaiting
approval.
4. Cleaning of Debris-T cdrn Thioccupied. Uncleaned Buildings
Objective: Since the debris removal from the immediate areas of destruction in the WTC complex
is nearing completion, the remaining unoccupied, uncleaned buildings must be cleaned
This will prevent debris/dust from being re-entrained in air and/or re-contaminating the
nearby area.s with debris/dust.
Program: NYC will clean the remaining unoccupied (residential and comn.ercial), unuleaned
buildings near the WTC site that contain WTC-debris. NYC will work with building
owners to determine reasons that these buildings have not been cleaned yet. If building
owners are not able to expeditiously clean their property, NYC will proceed.
Projected Cost: $20 million, based upon estimates approximately $2 million/building for 10
buildings. Inventory of buildings is being identified by NYC and may be decreased as a
result of NYC’s efforts to get building owners to conduct clean up.
Status ofRequestfor FEAf4 mission assignment: Awaiting initial FEMA feedback
5. Clean Up of Exteriors of Buildings with Residual Debris/Dust
Objective: To eliminate remaining debris/dust resulting from the WTC collapse on building
exteriors in Lower Manhattan thereby assuring this material will not become re-entrained
in the air at a future time, thus creating a potential exposure to the public.
Program: NYC DEP will contract for the cleaning of the exteriors of approximately 250
buildings in Low er Manhattan. EPA, NYCDEP and OSHA will oversee contractors.
Projected Cost: NYC $10.28 Million
Project Period: April 200? through November 2002
Status ofRequestfor FEA fl mission assignment: FEMA funding approved pending resolution of
indemnification issues.
6, Review of HVAC Systems in T.ower Manhattan,
Objective: To evaluate whether further actions are required for central, recirculating HVAC
systems in residential buildings in Lower Manhattan which may have been impacted by
the debris/dust from the WTC building collapse.
3