Internal DEP correspondence discussing EPA draft scope of work for WTC program and clarifying agency roles and responsibilities.

NYC-WTC_000138918–000138940

Folder label: “2003 E-Mails Sent M Gilsenan

Page image
Scanned page image, NYC-WTC_000138938
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Scope of Work B

Application: A visual inspection was performed and large or significant accumulations ofdust or debris from the collapse ofthe WTC was observed in common areas, residences or portions thereof(such as windows, terraces or balconies).

Residents will not be allowed in the work area. Residents may be present in the residence during cleaning in cases where the work area can be isolated by the erection ofisolation barriers. In all other applications of Scope B it is assumed that residents will not be present in the residence.

1. A site specific work plan will be prepared by the cleaning contractor for review and approval by EPA prior to the start ofwork. This work plan will include dctailedprocedurcs for the removal of dust and debris and the cleaning. At a minimum the procedures specified for a Scope A cleaning shall be implemented.

2. An asbestos project notification form (NYC form ACP-7) shall be submitted, as required by Title 15, Chapter 1 ofthe Rules ofthe City ofNew York (RCNY), directly to the NYC DEP Asbestos Control Program prior to the start of work. NYS DOL notification shall also be submitted.

3. At least one asbestos supervisor shall be present at each workplace (workplace is defined in Title 15, Chapter 1 RCNY as the work area and the decontamination enclosure system).

4. Personal protective equipment including disposable clothing, gloves, and respirators shall be worn during this cleaning activity.

5. Warning signs shall be posted at the approach to the work area.

6. A worker decontamination enclosure system shall be installed at the entrance to the work area. A remote decontamination enclosure system shall be considered when appropriate, i.e. inability to comply with the provision due to space limitation or other agency rules, such as for compliance with New York City Fire Department egress requirements.

7. HVAC systems shall be shut down and locked out or isolated locally. The site specific work plan shall provide additional information on the HVAC system and proposed procedures for shutdown or isolation.

8. Isolation barriers shall be installed with two layers of 6-mil polyethylene sheeting and sealed with tape.

9. Negative pressure ventilation equipment shall be installed and operated during all cleaning activities. Equipment shall run continuously until clearance air monitoring. A minimum ofone air change every

7

NYC-WTC_000138938

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000138938Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →