September 3, 2003
New York City Department of Environmental Protection
Attention: Virginia Smyth
59-17 Junction Boulevard
Flushing, New York 11373-5108
Re: Change Order Request
Project: 125 Cedar Street
NYCDEP Contract No. WTC-UNA
Dear Ms. Smyth,
ATC Associates Inc. (ATC) hereby requests approval of the previously submitted Change Order to the
original contract in the sum of $42,144.50.
ATC incurred additional costs on this project due to an increase in the required "quantity" of Project Monitor
time, Air Monitoring Technician time, PCMe — PCM — TEM sample analysis, and TEM analysis referenced
as items number 1, 2, 4, & 5 respectively within the contract spreadsheet. These quantities were established
by NYCDEP, and were exceeded in completing the scope of work for this project. A breakdown of these
additional costs is as follows:
Item No. Description of Item Unit Additional Unit Price Additional Cost
Quantity
1 Project Monitor Hour 17 $ 24.75 $ 420.75
2 Air Monitoring Hour 147.5 $ 22.50 $ 3,318.75
Technician
3 PCMe, PCM, TEM Sample 69 $ 5.00 $ 345.00
Analysis
4 TEM Analysis Sample 692 $ 55.00 $ 38,060.00
Total $ 42,14450
Should you have any questions or require additional information, please do not hesitate to contact me at (212)
353-8280.
Sincerely,
Benjamin M. Sallemi
Sr. Project Manager
NYC-WTC 000108050