NYC 9/11 Public Portal Document
SEP-25-2001 16 17 NYCSCR IEH 71B 472 8297 P.02/62
NEW YORK CITY SCHOOL.
CONSTRUCTION AUTHORITY
September 25, 2001
Rajaappan Radhaki ishnan
Director, Asbestos Control Program
NYC Department of Environmental Protection
59-17 Junction Boulevard, 8th Floor
Corona, New York 11368
Re: Clean-up at Stuyvesant H.S.
345 Chambers Street, New York., NY
Dear Mr. Radhakrishnan:
In response to a request from the Board of Education, the SCA will proceed with
clean-up of the subject school.
Work will be performed in two phases. The first phase will consist of cleaning the 6'
through 11th Floors, including the roof. The second phase will be from the 1 through
the 5th Floor.
Work will commence tomorrow, Wednesday, September 26, 2001 at 10:00am and will
continue until completion.
The scope of work includes the cleaning approximately 50,000 square feet. We will
utilize two contractors, Trio Asbestos Removal Corp. and Kiss Construction Co. The
consultants will be ATC Environmental and Taylor Environmental Group.
Based on our discussion, the SCA will isolate the 6d' floor from the rest of the building
and we will use one decon per floor.
On the first day of work, we will perform monitoring outside the building. At the end
of the clean-up, we will perform clearance monitoring. All results will be provided to
the DEP.
If you s uld hive any questions relating to the above information, please feel free to
contac a at 18) 472- 8501. Thank you.
r Lempert
I&EH Division
30-30 Thomson Avenue
Long Island City, NY 11101.3045
718 472-8000
PsY '71 R a77-RRdn
TOTAL P.02
NYC-WTC 000106889
OCR can misread numbers and units. Confirm readings against the page image before using them.