Scope of work document for 114 Liberty Street interior cleaning,

Machine-extracted title · confidence 95%

Scope of work document dated February 2003 detailing a mandatory pre-bid meeting and requirements for asbestos abatement contractor cleaning at 114 Liberty Street.

NYC-WTC_000102620–000102631

Folder label: “SCOPE OF WORK ADDENDUMS WORK SCHEDULE

Page image
Scanned page image, NYC-WTC_000102625
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

New York City Department of Environmental Protection Bureau of Environmental Compliance

WTC Unoccupied Building Cleaning Program 114 Liberty Street Scope of Work Project #WTC-LBA

A MANDATORY PRE-BID meeting is scheduled for February 18, 2003 at 10:00 A.M. at 114 Liberty Street, Building Lobby, New York, N.Y. This conference will include a walk through of the entire building.

Background

A follow-up visit to 114 Liberty Street revealed minor dust accumulations present on surfaces within the interior of the building. The interior cleaning is to be accomplished by a licensed asbestos abatement contractor and monitored by a Monitoring Contractor.

Purpose

The Monitoring Contractor shall provide personnel experienced, trained, and certified in environmental sampling and asbestos air monitoring to be on-site, full-time, during work area preparation and cleaning phases of building interiors (12 stories —5,000 to 6,000 square feet per floor). Each apartment occupies an entire floor with the exception of the top floor that is a duplex and the apartment on the third floor that shares the floor with two commercial spaces. The entire interior of the building (residential, commercial, retail spaces, common spaces, etc.) is included in this work. Each floor has central HVAC systems.

The Monitoring Contractor shall provide qualified staff to observe the work, conduct air monitoring and sampling, and monitor the cleanup of the building interiors to ensure compliance with the project specifications and appropriate regulatory requirements. The Monitoring Contractor shall provide clearance sampling and analyses.

The Monitoring Contractor shall provide qualified staff to collect samples for asbestos, lead, polyaromatic hydrocarbons (PAHs), dioxin, fibrous glass, and crystalline silica.

An accredited laboratory shall perform all sample analyses.

Contract Term

The Work shall be performed 24 hours per day, seven (7) days per week. Pre-clean up sampling must begin within 24 hours of receipt of the Commence Work letter. All pre-clean up samples must be completed and submitted to the laboratory for analysis within 48 hours. This contract be in force for 90 consecutive shall

calendar days from the DEP commencement date. However, work must be completed within three (3) weeks of the commencement date. Post clean up sampling shall begin within 4 hours of successful visual inspection and shall be completed within 2 days.

1 of 7 2/7/03

NYC-WTC 000102625

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000102625Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.