Folder label / City-provided: Change Order 44R Mayor's Office of Emergency Management 7 World Trade Center New York, New York
3 documents · 6 pages
Change Order #44R approval, fuel pipeline, 7 WTC, April 1999 ↗
2 pagesNYC-WTC_000168435 – NYC-WTC_000168436
DCAS approves a reduced cost of $85,000 for the supply and installation of a fuel pipeline at 7 World Trade Center.
Memo approving change order #44R for fuel pipeline, April 1999 ↗
2 pagesNYC-WTC_000171316 – NYC-WTC_000171317
City memo approving a negotiated cost of $85,000 for the supply and installation of a fuel pipeline at 7 World Trade Center.
Change Order #44R approval letter, 7 WTC, April 1999 ↗
2 pagesNYC-WTC_000171754 – NYC-WTC_000171755
DCAS approval letter for Change Order #44R regarding fuel pipeline installation at the Mayor's Office of Emergency Management.